基础开挖作业指导书

来源:易妖游戏网


基础开挖作业指导书

编码:PDFTJ-02

目 次

1 2 3 4

适用范围 ····················································································································· 1 编写依据 ····················································································································· 1 作业流程图 ·················································································································· 1 安全风险辨析与预控 ······································································································ 1

5 作业准备 ····················································································································· 2 6 作业方法 ····················································································································· 2 7 质量控制措施及检验标准 ································································································ 7

1 适用范围

本节适用35kV及以下配网工程配电房(油池)的基础土石方开挖。 2 编写依据

表2-1编 写 依 据

序号 1 2 3 4 5 引用资料名称 GB 50204—2002《混凝土结构工程施工质量验收规范》 JGJ 79—2002《建筑地基处理技术规范》 GB 50202—2002《建筑地基基础工程施工质量验收规范》 Q/CSG 11105—2008《南方电网工程施工工艺控制规范》 《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》 3 作业流程图

图3-1作业流程图

4 安全风险辨析与预控

表4.1 工作前安全风险辨析及预控措施表 序安全风险 号 预控措施 施工方案中要明确规定基坑内不许多人同时作业 1 坍塌 两人同时作业时不得面对面作业 检查结果 雨水后土质松软容易塌方施工时应使用挡土板,并派专人安全监护, 随时检查坑边是否有裂纹、挡土板有无变形或断裂现象 保持安全距离,设专人监护。基坑开挖时应将基面上浮石、松石或坑边浮石、土块清除掉,避免施工时活石掉下砸伤人 2 物体打击 采用打风镐等机械方式开挖水泥路时,施工人员应戴安全帽,手套与 面罩,采用人工方式,打铁锤人应站在扶凿人的侧面,不得戴手套,并应采取有效防围墙防止时刻弹起伤人 避开中午炎热时间段户外作业 中暑 配置太阳伞,室内配置排风扇,人员轮流休息 供应清凉含盐饮料 3 4 触电 加强使用前几使用过程中的检查,保护零线与工作零线不得混接,开 关箱漏电保护器灵敏可靠,漏电保护装置参数匹配,严格执行“一机、一闸、一漏、一箱”的要求 用电管理和检修维护必须规范,并由专业电工进行,配电箱必须上锁, 并采取防雨措施 请您认真检查并签名确认,您的签名意味着将承担相应的安全质量责任。

施工单位检查人: 监理单位检查人: 日期: 日期:

注:对存在风险且控制措施完善填写“√”,存在风险而控制措施未完善填写“×”,不存在风险则填写“—”,未检查项空白。

5 作业准备

5.1 作业前施工条件

表5-1 作业前施工条件

序号 1 2 3 项目 任务单 相关证照 工程合同 或协议 内 容 根据本单位实际设置内容(包含本项工作) 根据需要办理涉及进入工作场所的手续、证件 合同及安全协议 确认人 本工序施工负责人 本工序施工负责人 本工序施工负责人 说明 经审批 有效 有效 4 5 图纸 施工方案 设计图纸 施工措施、安全技术交底(项目部级) 本工序施工负责人 本工序施工负责人 经审批 经审批

5.2 人员、主要工器具及仪器仪表配置

表5-2 人员、主要工器具及仪器仪表配置

序号 1 项目 人员配置 施工内容 相对应的设备材料 施工内容 相对应的器具、机械及工器具仪表 完成开工 程序 内 容 施工员、施工作业人员等 说 明 技术岗位必须持有与作业工种相应、有效的上岗证 必须符合设计要求 2 施工所需材料 3 施工所需的工器具、机械、测量仪器等 根据现场情况使用的工器具、机械、仪器、文明施工用具等应符合相关要求 施工准备完成后可报开工,当施工准备不足时,上报该项目负责人协调解决 4 工作负责人向项目负责人报开工,并由项目负责人完成向监理单位开工报审手续

6 作业方法

表6-1作业方法

序号 项目 内 容 说 明 1 (1) 土方开挖前应详细查明施工区域的地下、地上障碍物,对位于基坑内的管线和相距较近的地上、地下障碍物已按拆、改或加固方案处理完毕。 (2) 基坑或管沟的定位控制线、水准基点已测设完毕,并经预检合格,已放好开挖灰线。 (3) 基坑(槽)位于地下水以下时应提前降水,将水位降至开挖底面下500mm后方可进行土方开挖。 按安规规定佩戴统一的安全 (4) 现场施工负责人向进入本施工范围的所有工作人员明帽,统一佩戴有个人照片的作业作业前工作 确交待本次施工设备状态、作业内容、作业范围、进度要求、证(或胸卡证),穿着统一的工作特殊项目施工要求、作业标准、安全注意事项、危险点及控服 制措施、危害环境的相应预防控制措施、人员分工,并签署(班组级)安全技术交底表。 (5) 现场施工负责人负责办理相关的工作许可手续,开工前做好现场施工防护围蔽警示措施;夜间施工的须有足够的照明。 (6) 现场施工负责人组织检查确认进入本施工范围所有工作人员是否正确使用劳保用品及着装,并带领施工作业人员进入作业现场 2 开始主要 作业 现场施工负责人发出许可开工命令 (1) 基础开挖坡度的确定,应先测量定位,找平放线,定出开挖宽度,按放线分块(段)分层挖土。根据土质和水文情况,采取四侧或两侧直立开挖或放坡,以保证施工操作安全。 (2) 当土质在天然湿度、构造均匀、水文地质条件良好(即不会发生坍塌、滑动、松散或下沉)且无地下水时,开挖基坑可不放坡,采取直立开挖且不加支护。基坑(槽)和管沟不加支撑的允许深度详情见下表。 序号 1 2 3 4 土 的 种 类 密实、中密的砂子和碎石类土(充填物为砂土) 硬塑、可塑的粉质黏土及粉土 硬塑、可塑的黏土和碎石类土(充填物为黏土) 坚硬的黏土 允许深度 m 1.00 1.25 1.50 2.00 现场施工负责人正确、安全地组织作业,现场施工质安员负责现场作业全过程的安全规范和质量跟踪 3 (3) 当土质略为松散,或超过上表规定的深度,但不大于2.5m时,应根据土质和施工具体情况进行放坡处理,以保证确定开挖 不塌方,其放坡坡度选用值应按下表实施。放坡后基坑上口顺序、坡度 宽度是由基坑深度及边坡坡度值来确定,坑底宽度每边应比基础底宽出20~25cm,以便于施工操作 深度在2.5m内的基槽管沟坡的最陡坡度如下表所示。 边坡坡度容许值(高:宽) 土的类别 坡顶无荷载 1:1.00 l:0.75 l:0.67 1:0.50 1:0.33 l:0.10 1:1.00 坡顶有静载 1:1.25 1:1.00 1:0.75 l:0.67 1:0.50 1:0.25 — 坡顶有动载 1:1.5 1:1.25 1:1.00 1:0.75 1:0.5 1:0.33 — 中密的砂土 中密的碎石类土 (填充物为砂土) 硬塑的粉土 中密的碎石类土 (填充物为砂土) 硬朔的粉质黏土、黏土 老黄土 软土(经井点降水后) 4 基坑开挖 (1) 开挖基坑(槽)或管沟时,应合理确定开挖顺序、路线及开挖深度,分段分层均匀开挖。 (2) 采用挖土机开挖基坑(槽)时,应从上而下按照坡度线向下开挖,严禁在不稳定土体之下作业,每层的中心地段应比两边稍高一些,以防积水。 (3) 在挖方边坡上如发现有软弱土、流砂土层,或地表面出现裂缝时,应停止开挖,并及时采取相应补救措施,以防止土体崩塌与下滑。 (4) 挖土机沿挖方边缘移动时,机械距离边坡上缘的宽度不得小于基坑(槽)和管沟深度的l/2。 土方开挖时防雷接地网敷设应 (5) 机械开挖基坑(槽)和管沟,应采取措施防止基底超同步进行。防雷接地网工程详见挖;机械开挖至接近设计标高时,应预留200~300mm厚土PDFTJ-17防雷与接地作业指导书 层,用人工开挖,以防发生超挖影响持力层的质量要求。 (6) 施工过程中严格按设计图施工,严禁超挖。如发生超挖,应首先将松动部分清除,然后妥善处理:超挖深度小于100mm时,采用原状土或石屑(或粗砂)回填压实至设计标高并夯实;超挖深度再大时,应报监理、设计及建设单位处理。 (7) 机械挖不到的土方,应配以人工挖掘。挖出的土方应随挖随清,槽边1.0m以内不得堆土,并不得堆料和停置机具。槽边2m以外堆土不得大于1.5m。距槽边0.5m应搭设防护措施 配电房工程中,基坑支护形式一般采用连续式水平支撑支护,挡土板与被支护土方水平放置,相互紧靠,不留间隔,然后两侧同时对称立上竖木枋,上下各顶一根撑木,撑木的排列位置选择以减少影响后面工序施工为宜,端头木锲要加钉子固定 5 基坑支护 6 (1) 土方开挖一般不宜在雨期施工,如必须在雨期施工时,开挖工作面不宜过大,一旦开挖即应连续快速进行。 (2) 雨期施工开挖的基坑(槽)或管沟,应注意边坡稳定排(降)水 及对沟底持力层的保护。 (3) 在基础外侧挖集水井,将基坑的地下水引入集水井,用潜水泵排走 在距基槽底实际标高500mm槽侧处,抄出水平线,钉上小木橛,然后用人工将暂留土层挖走。同时由两端轴线(中心修坡和清底 线)引桩拉通线(用小线或铅丝),检查距槽边尺寸,确定槽宽标准。以此修整槽边,最后清理槽底土方 7 7 质量控制措施及检验标准 7.1质量控制措施

7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。

7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。

7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措施。

7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。 7.1.5施工质量检验一般按以下方式进行。质量检验一般采用三级检验制,施工队(组)对所施工的分项工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。 7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。

7.2质量控制点

表7.2 质量控制点表单

序号 项目 内 容 1 本工序完成后,现场施工负责人按照中国南方电网公司Q/CSG 10017.3-2007本工序工艺《110kV~500 kV送变电工程质量检验及评定标准 第3部分:变电土建工程》检验 中表5.3.1的规定执行和根据表5-4中序号2质量控制点要求生成相关表格,并组织检验 控 制 方 式 序号 控制点 W 1 2 3 4 控制桩设置 平面控制桩精度 高程控制桩精度 边坡坡度偏差 标高偏差 长度、宽度(由设计中心线向两边量)偏差 土方开挖顺序、方法 标高偏差 排水、降水 工序验收检查 ● ● ● ● ● ● ● ● ● H ● S 2 质量控制点 5 6 7 8 9 10 3 完成本工序提交给下一道工序 收集、整理、移交本工序相关资料 注:质量控制点中H:停工待检点;W见证点;S旁站点。

因篇幅问题不能全部显示,请点此查看更多更全内容