您好,欢迎来到易妖游戏网。
搜索
您的当前位置:首页7#塔吊基础施工方案

7#塔吊基础施工方案

来源:易妖游戏网
成都珠江新城国际A区工程7#塔吊基础施工方案

目录

1. 方案替换原因说明 ···················································································· - 1 - 2.编制依据 ······································································································ - 1 - 3.工程概况 ······································································································ - 2 -

3.1工程项目基本概况 ··························································································································· - 2 - 3.2工程概况 ··········································································································································· - 2 - 3.3 7#塔吊基础定位情况说明 ················································································································ - 3 -

4. 7#塔吊施工的前期准备 ··············································································· - 3 -

4.1工程地质概况 ··································································································································· - 3 - 4.2塔吊基础说明 ··································································································································· - 4 - 4.3塔吊基础施工要求 ··························································································································· - 4 -

5. 7#塔吊基础施工 ························································································· - 6 -

5.1塔吊基础工程 ··································································································································· - 6 - 5.2钢筋工程 ··········································································································································· - 7 - 5.3混凝土工程 ······································································································································· - 7 -

6.质量保证措施······························································································· - 8 - 7.安全、消防管理及文明施工 ········································································· - 8 - 8.其它注意事项······························································································· - 9 - 9.附图 ··········································································································· - 10 -

- 1 -

成都珠江新城国际A区工程7#塔吊基础施工方案

1. 方案替换原因说明

我司于2012年4月11日,将《成都珠江新城国际A区工程7#塔吊基础施工方案》上报给贵司。2012年4月16日,贵司经审批,同意按此方案施工7#塔吊基础。随后,我司立即与塔吊公司联系,委托其加工塔吊基础马凳及预埋节等。2012年11月10日,我司收到贵司下发的二、三期新版蓝图。图中标明A2#楼筏板基础厚度加厚。因7#塔吊基础顶位于核心筒筏板底标高之下,故塔吊基础会随筏板厚度加厚而下降,基础埋深加深。

因此,7#塔吊基础埋深与原申报方案不符,原申报方案作废。我司根据贵司2012年11月10日下发的新版蓝图和2012年11月27日下发的《A2、A3电梯基坑大样修改》(图号:001,修改码:改11)重新编制完成7#塔吊基础施工方案。

2.编制依据

1、成都珠江新城国际A区工程提供的相关图纸及数据。 2、现行国家及成都市有关部门相关标准及规范、规定: (1)《塔式起重机》(GB/T5031-2008); (2)《塔式起重机安全规程》(GB5144-94); (3)《塔式起重机技术条件》(GB/T9462-1999); (4)《建筑地基基础设计规范》(GB50007-2002); (5)《混凝土结构设计规范》(GB50010-2002);

(6)《建筑地基基础工程施工质量验收规范》(GB50202-2002); (7)《电气安装工程施工及验收规范》(GBJ232); (8)《塔式起重机操作使用规程》(JGT100—1999); (9)《施工现场临时用电安全技术规范》(JGJ46-2005); (10)《建筑机械使用安全技术规程》(JGJ33-2001); (11)《施工现场临时用电安全技术规范》(JGJ46-88);

(12)《TC7035B塔式起重机安装使用说明书》(塔吊厂家提供的技术资料以及数据和图纸);

(13)现场勘察报告《珠江新城A区工程岩土工程详细勘察报告》(中南勘察设计院(湖北)有限责任公司);

- 1 -

成都珠江新城国际A区工程7#塔吊基础施工方案

(14)城乡建设环境保护部关于加强塔式起重机安全使用管理的若干规定; (15)其它成都市相关文件要求。

3.工程概况

3.1工程项目基本概况 序号 1 项 目 工程名称 内 容 成都珠江新城国际A区 成都市温江区东部“珠江新城国际项目”内(光华大道与天宝中街交汇处),东距成都三环路14公里,西距温江老城区中心约2公里,南接光华大道,北侧为燎原路。 成都珠江创展投资有限公司 成都市温江区建设工程质量监督站 广东珠江建设工程监理有限公司 中国建筑一局(集团)有限公司 北京中建正和建筑机械施工有限公司 2 地理位置 3 6 7 8 9 建设单位 监督单位 监理单位 施工总包 塔吊施工单位 3.2工程概况

由我局承建的成都珠江新城国际A区工程(以下简称“本工程”),其一期工程为A0和A4#楼,在结构施工阶段需用5台塔式起重机配合施工;二期工程为A1、A1.5、A2、A3#楼,在结构施工阶段需用3台塔式起重机配合施工。为确保安全顺利地完成塔吊施工,项目部技术人员经过对施工现场的实际勘察及与塔吊安装技术人员会研,编制《成都珠江新城国际A区工程7#塔吊基础施工方案》(以下简称《方案》),用以指导塔吊基础的施工作业。

本工程总建筑面积达72.3万㎡,地下室总面积约为21.7万㎡,地上建筑总面积约为50.6万㎡;其中,一期地上建筑面积约19万㎡,地下建筑面积约为13万㎡;二期地上建筑面积约31.6万㎡,地下建筑面积约为8.7万㎡。整个地块主要配置由四栋超高层办公塔楼和商业mall组成,依次从地块的西侧沿南北走向依次布置,高度从南往北降低,与用地北面D地块的塔楼共同构成一个高层带,以A1塔楼(230m)为起点标志。地块的东侧为大型商业mall,是包含大型百货商场、

- 2 -

成都珠江新城国际A区工程7#塔吊基础施工方案

影院、零售商业、餐饮、娱乐为一体的商业综合体。

本工程的高层部分为A1、A2、A3、A4#塔楼,A1#楼为办公楼,高度为231.70m,地上总层数为53层,标准层高为4.20m;A2#楼为公寓楼,高度为1.00m,地上总层数为54层,标准层高为3.30m;A3#楼为公寓楼,高度为161.70m,地上总层数为46层,标准层高为3.30m;A4#楼为办公楼,高度为148.25m,地上总层数为35层,标准层高为3.90m。本工程的商业部分为A0、A1.5#楼,A0高度为31.65m,地上总层数为4层,局部为5层;A1.5高度为12.10m,地上总层数为2层;地下室为3层,基底标高为-16~-28米。 3.3 7#塔吊基础定位情况说明

本工程总基地面积约为7.6万㎡,建筑体量相当巨大,根据本工程料场位置、裙房分部等情况,尽最大限度确保满覆盖,充分利用好每台塔吊,本着“合理利用空间和平面、优化总体施工进度计划、科学合理部署”的原则,设置塔吊的幅度及定位。7#塔吊由TC7035B塔吊配合施工,臂长为70m。塔吊基础的具体位置详见《成都珠江新城国际A区工程塔吊平面布置图》,以及7#塔吊的《塔吊基础平面定位图》。

4. 7#塔吊施工的前期准备

4.1工程地质概况

根据《珠江新城A区工程场地岩土工程勘察报告》,本工程场地地势开阔,地形平坦,交通便利,地貌单元属川西平原岷江水系Ⅰ级阶地,地基土层从上而下依次为杂填土层、粉土、细砂、卵石层。各土层主要物理力学性质指标见下表:

各岩土层物理力学参数值建议表 表3.1-1

岩土体与锚岩 土 名 称 重度 γ(kN/3m) 压缩 模量 Es(MPa) 变形 模量 E0 (Mpa) 粘聚力C (kPa) 内摩擦角承载力特征值固体的极限oφ() fak(kPa) 摩阻力标准值qsk (kPa) 杂填土 粉土 细 砂 18.0 19.0 18.5 4.7 5.0 地基基床系数 K (KN/m) 3 16.0 11.0 20 130 110 10 40 45 - 3 -

成都珠江新城国际A区工程7#塔吊基础施工方案

松散卵石al+pl(Q4) 稍密卵石al+pl(Q4) 中密卵石al+pl(Q4) 密实卵石al+pl(Q4) 20.0 20.5 22.0 23.0 14.0 22.0 32.0 45.0 25 35 40 45 180 320 550 850 80 100 200 250 2.5×10 3.5×10 4.5×10 6.0×10 4444水文地质条件:

场地内地下水主要为杂填土层中上层滞水和砂卵石层中潜水两种。砂卵石层为主要含水层,透水性强,水量丰富, 卵石层渗透系数建议值为K=22~25.0m/d。地下水主要由大气降水和地下迳流补给,水位随季节改变而变化。施工期间由于临近场地工地降水作业影响,场地地下水位极不稳定,测得场地地下水位深5.7~8.5m,相应标高介于520.019~522.997m。根据成都地区水文地质资料,场地地下水年变化幅度为1.0-2.0米,因此场地抗浮设防水位建议按绝对标高527.5m考虑。

根据《珠江新城A区详勘报告2010.7.15日(最终稿)》,其7#塔吊位置处于1-1和2-2剖面图的范围内,其中,7#塔吊的基础底相对标高为-23.450,绝对标高为506.23,而1-1、2-2图中表示,在绝对标高506.23位置,属于密实卵石层,其地基承载力为850kpa,符合塔吊基础地基承载力要求。 4.2塔吊基础说明

1、采用预埋节形式,为尽早安装和利用塔吊,塔吊基础采取先行施工的方式,即在基础底板施工前就完成塔吊安装施工。为保证塔吊基础施工及塔吊安装能够顺利完成,要在施工现场西北角入口预留坡道,且路面宽度不小于5米、坡度不大于1:6,并有不小于15×15米转弯半径,路面及站位面需足够硬实和平坦。

2、7#塔吊基础说明

7#塔吊基础设置在建筑物基础筏板以下,塔吊基础自下而上做法为:100厚的C15砼垫层→C35塔吊钢筋混凝土基础→SBS防水卷材层→50厚C20细石混凝土防水保护层→A2#楼基础筏板。

3、塔吊基础施工完成后,根据同条件混凝土强度试验确定塔吊安装时间。 4.3塔吊基础施工要求

1、塔吊固定式混凝土基础制作和预埋节的安装

(1)塔吊形式:采用承台固定式混凝土基础,设置在防水底板以下。 (2)基础图:根据勘察单位提供的基坑底部的密实卵石承载力特征值

- 4 -

成都珠江新城国际A区工程7#塔吊基础施工方案

fak=850kPa,大于塔吊基础所需的地基承载力200kpa,确定7#塔吊(型号为TC7035B)基础垫层做法为100厚的C15素混凝土,基础尺寸为6250×6250×1400,基础混凝土强度等级为C35,基础配筋为上排钢筋为双向C25@120,下排钢筋为双向C25@120,上下排钢筋设置C20@480的拉筋,具体详见北京中建正和建筑机械施工有限公司提供的塔吊基础配筋图。

(3)基础技术要求:

1)混凝土基座以下土壤的承载力要求: 混凝土基础以下的土壤的承载力不小于200Kpa 2)混凝土基座技术要求:

混凝土基础尺寸不小于6250×6250×1400mm³ 水泥含量:350Kg/m³ 水泥标号:425 基座比重:2.4 混凝土强度等级:C35

混凝土表面校平,平面度误差应不小于1/500。

要求对塔吊基础的承载面进行平整处理,塔吊基座以下不得有管道、洞穴等;基础的钢筋网配筋应严格按照图纸要求进行施工,不得减少。

在进行塔吊预埋节安装时预埋节上平面与塔吊混凝土基础面垂直尺寸为350±5mm。预埋节四个角上平面的平面度不大于1/1000。

(4)塔吊基础开挖:

根据定位图、塔吊基础图及塔机预埋节砼基础承台图,确定开挖塔吊基础坑尺寸和深度。对基坑进行平整处理,并打100厚的 C15垫层。

(5)基础施工过程及预埋节的安装:

1)在混凝土基础布完下层钢筋后,把支撑马凳与混凝土基础下层钢筋焊连(支撑马凳的制作见《塔机马凳图》),再使用16t汽车吊吊装塔吊预埋节,按附图所示安装预埋节,经测量(工程施工单位配合测量,须保留测量结果)、调整达到技术要求后,把预埋节与支撑马凳焊连,然后再布其余钢筋,最后浇注混凝土。

2)塔吊预埋节的安装尺寸及安装方法 技术要求:

a.预埋节的四个支脚的同一高度尺寸的四个销孔的中心线应在同一平面内,

- 5 -

成都珠江新城国际A区工程7#塔吊基础施工方案

允许公差≤孔间距的1/6500,四个孔两两之间的绝对公差≤0.3mm;

b.预埋节角钢上平面与塔吊混凝土基础面垂直尺寸150±5mm; c.预埋节主角钢垂直于基座,公差≤1/1000;

d.基座表面平整,平面度公差在2m×2m平面内小于3mm; e.预埋节周围的钢筋数量不得减少。 2、预埋节支撑马凳制作

根据预埋节埋设深度,预埋节的支撑马凳在现场用L30和L80的角钢,按照马凳设计图纸焊接而成,塔机马凳图见《马凳制作参考图》。

3、塔吊的接地装置

在塔吊基础周围采用φ45×45mm长2.5m的镀锌角钢专用接地极,打入地下2m(三组),然后与塔吊基础预埋节上的四个固定支脚连接。须保证接地电阻不大于4Ω。该项工作由工程施工单位完成。

4、塔吊楼板预留洞设置要求

因7#塔吊为A2#楼的内爬塔,塔身部分必须穿越楼板结构。在塔节穿过楼板时,按规范要求将楼板钢筋断开,并在洞口四周每侧增加4根25钢筋,上下各两根。待塔吊往上爬升或拆除后,留出封堵楼板的工作面,再按规范要求将断开的钢筋连接,进行洞口的封堵。封堵时,浇筑比设计强度等级高出一级的无收缩防水混凝土。

5. 7#塔吊基础施工

5.1塔吊基础工程

1、塔吊基础埋设在结构筏板以下,在塔吊基础施工时,采用以土带模施工方法进行塔吊的基础的施工。

2、塔吊基础开挖时,由于7#塔吊位置处的A2#楼筏板基础的底标高为-22.000,开挖标高将在-22.150位置。施工时,塔吊基础周边预留3m厚的土层,即整个A2筏板基础先开挖至-19.050标高,然后再开挖7#塔吊基础。7#塔吊基础四周先采用1:1放坡至-22.050标高,然后进行塔吊基础的土模施工。

3、塔吊土模施工时,塔吊基坑放直坡,必要时采用支撑对边坡进行加固处理,并且土模的尺寸要大于塔吊基础图的尺寸,即大于6250×6250×1400 mm³。

土模施工时,东、西、北三面为土模,南面为240mm厚砖胎模,详附图。

- 6 -

成都珠江新城国际A区工程7#塔吊基础施工方案

4、在塔吊基础开挖时,可能地下水位会高于-23.550。如果开挖时发现地下水渗出,在塔吊基础的角上设一净空为400×400×800的小集水坑,将基础内的积水引流到小集水坑中,再用抽水泵将水抽出。

5、抽出的地下水先集中到地面上的集水坑内,然后再抽到市政雨水管道内,以免水流过大,对塔吊周围的土方造成安全隐患。

6、由于土方开挖深度较大,在塔吊基础开挖后,应排专人对塔吊基坑搭设临边安全防护。

7、塔吊基坑开挖后,还应在1:1坡体上覆盖双层大眼网,防止坡体上的石块滑落坑底对施工人员造成伤害。

土方开挖详见附图。 5.2钢筋工程

1、核对成型钢筋:钢筋制作后,要按设计图纸核对加工的半成品钢筋。对其规格、形状、型号、品种进行检验,然后挂牌堆放好。

2、钢筋绑扎:钢筋应按顺序绑扎,要先短向后长向,由一端向另一端依次进行。操作时按图纸要求划线、铺铁、穿箍、绑扎,最后成型。

3、预埋节位置应正确,塔吊基础配筋应按图纸绑好,绑扎要牢固,应采用十字口绑扎或焊牢,其标高、位置、搭接、锚固长度等尺寸应准确,不得遗漏和移位。

4、受力钢筋搭接接头位置正确。其接头应相互错开。每个搭接接头的长度的1.3倍范围内,搭接钢筋面积不应超过该长度范围内钢筋总面积的不应超过长度范围内钢筋总面积的1/4。所受力钢筋和箍筋交接处全绑扎,不得跳扎。

5、垫块:底部钢筋下垫混凝土垫块,保护层的厚度不小于50mm,每隔1m放一块,混凝土垫块应与钢筋绑牢扎固,不应遗漏。

6、钢筋需办隐检手续。 5.3混凝土工程

1、浇灌:浇灌之前,抽水泵应处于工作状态,应确保坑底无积水。浇灌时,可同时采用2辆混凝土罐车同时使用溜槽进行浇筑,按顺序直接将混凝土倒入土模中,以减少浇筑时间。浇筑时,严格进行分层施工,防止冷缝,每个塔机基础必须一次浇灌完成,不许留施工缝。

- 7 -

成都珠江新城国际A区工程7#塔吊基础施工方案

2、振捣:应沿基础浇筑的顺序方向,采用斜向振捣法,振捣棒与水平倾角为60°左右,棒头朝前进方向,棒间距以500mm为宜,防止漏振,振捣时间以混凝土表面翻浆出气泡为宜。混凝土表面应随振捣随标高线用木抹子搓平压实,用铁抹子清光。

3、养护:混凝土浇灌后,在常温条件下12h内应覆盖浇水养护,浇水次数保持混凝土润湿状态为宜,养护时间不少于7昼夜。施工时要提前备好养护用品;在混凝土浇筑完成后,检查预埋件的情况,并根据情况进行调整,保证预埋件的误差不大于2mm。

6.质量保证措施

1、质量管理目标:加强管理,严格施工、精心操作。加强对每道工序的质量控制工作,采用先进的施工技术,提高工程质量,确保整体工程质量优良。

2、建立健全的质量保证体系和工程质量委员会。项目经理任主任,技术负责人任副主任,由技术、质量、材料等人员为成员,组织质量管理工作,处理重大工程质量事故。项目配置专职质检员,组织班组自检,开展全面的质量管理工作,全面按质量保证体系运作。

3、建立正常的质检制度、技术交底制度。施工前进行技术交底,内容包括图纸交底和各工种的技术交底。

4、坚持三检制度和执行隐蔽工程检查制度。班组自检、互检和交接检与专职检查相结合,充分尊重质检员的意见;凡隐蔽工程施工时必须进行验收合格签字后才能进行下道工序的施工。

5、工程施工中的每一道工序,均执行质量交底和技术交底制度,并作好记录。 6、执行“三检制”,每道工序必须填写质量检验评定表。

7、及时、准确作好各项施工的原始记录,以便发现问题,及时进行解决。 8、按照建设单位和工程监理要求的验收程序验收项目,进行质量过程控制,做好自检和申报验收,并交验各种资料,填报各种质量表格。

7.安全、消防管理及文明施工

1、方针目标

在施工中,始终贯彻“安全第一、预防为主”的安全生产工作方针,认真执

- 8 -

成都珠江新城国际A区工程7#塔吊基础施工方案

行、建设部、成都市关于建筑施工企业安全生产管理的各项规定,把安全生产工作纳入施工组织设计和施工管理计划,使安全生产工作与生产任务紧密结合,保证职工在生产过程中的安全与健康,严防各类事故发生,以安全促生产。

强化安全生产管理,通过组织落实、责任到人、定期检查、认真整改,实现杜绝人身伤亡事故和重大机械设备损坏事故、不发生火灾事故及其它重大事故,重伤率为零,轻伤率控制在一人次内,安全帽正确佩戴率为100%,严格控制各种习惯性违章的管理目标。

2、组织管理

(1)安排专职的且经验丰富的安全员,负责施工现场的安全生产管理工作。 (2)我方安全员需经常对施工现场安全生产进行检查。 3、管理制度

(1)成立施工安全领导小组,设立专(兼)职安全员,安全员有权对现场内任何违反安全操作规程及规定的人员进行处罚。

(2)职工入场前进行技术、安全交底,定期进行安全教育,做好安全教育记录,做到施工中责任明确,行动统一。

(3)管理人员及特种作业人员持证上岗,进入现场的民工要有三证。 (4)施工场区要有安全标识,挂牌警示,夜间应张挂红灯,划定安全通道。 (5)按照各工种作业要求正确穿戴个人防护用品。人员进入现场戴安全帽。 (6)机械设备及安全防护器具等做定期检查、保养,及时维护并记录,做到不带病作业。

(7)现场用电应严格按照用电安全管理规定,电工专人管理。每天对供电设施进行检查。

(8)多工种同时作业时要安排好流水段以免互相干扰,严禁立体交叉作业。 (9)正确使用防护装置及保护设施,不得任意拆除、随意挪动各种防护设施、警告牌和安全标志等。

8.其它注意事项

1、起重作业时,信号工在发出指挥信号以前必须事先观察好周边的作业状态,严禁起重臂下站人。

2、预埋节运达现场后,应组织技术、工程、质量与提供单位进行检查,确保

- 9 -

成都珠江新城国际A区工程7#塔吊基础施工方案

型号、规格的准确。

3、塔吊顶板预留洞周边严禁堆放重物,周边顶板下应设置临时脚手架支撑。为避免雨水流入地下室,在洞口周边砌10cm高挡水台。塔身周边洞口用18cm厚多层板进行临时封闭,避免杂物坠落伤人。

4、塔吊安装前,需将留置的同条件试块进行抗压试验,只有当达到塔吊施工企业提出的强度要求时,方可组织安装。

5、土模施工时,塔吊基坑周边严禁堆载,坑下施工作业人员要随时注意基坑情况,当遇到出现土体松动情况时,及时通过预先准备的救援梯撤出坑内,并在下一次开挖时,采用木模对坑边进行加固。

9.附图

- 10 -

成都珠江新城国际A区工程7#塔吊基础施工方案

- 11 -

成都珠江新城国际A区工程7#塔吊基础施工方案

- 12 -

成都珠江新城国际A区工程7#塔吊基础施工方案

- 13 -

成都珠江新城国际A区工程7#塔吊基础施工方案

- 14 -

成都珠江新城国际A区工程7#塔吊基础施工方案

- 15 -

成都珠江新城国际A区工程7#塔吊基础施工方案

- 16 -

因篇幅问题不能全部显示,请点此查看更多更全内容

Copyright © 2019- vipyiyao.com 版权所有 湘ICP备2023022495号-8

违法及侵权请联系:TEL:199 18 7713 E-MAIL:2724546146@qq.com

本站由北京市万商天勤律师事务所王兴未律师提供法律服务